Summer Academy production 2018: Difference between revisions
No edit summary |
|||
Line 3: | Line 3: | ||
* Duration: March 1th - August 10th (25 weeks) | * Duration: March 1th - August 10th (25 weeks) | ||
* Production / project owner: Anja & Isabel | * Production / project owner: Anja & Isabel | ||
* Deliverables (subject to change and suggestions) | * Deliverables (subject to change and suggestions) | ||
Line 10: | Line 10: | ||
* Correspondence with the location (DEK WEST) regarding production | * Correspondence with the location (DEK WEST) regarding production | ||
* | * Making inventory of material/equipment/electronics etc necessary | ||
* Gather and order | * Gather and order material/equipment | ||
* Arrange caterer for lunch and welcome dinner HDSA 2018 | * Arrange caterer for lunch and welcome dinner HDSA 2018 | ||
* | * Possibly arrange a cleaner (maybe arranged via Dek West?) | ||
* Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.) | * Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.) | ||
* Sort out funding possibilities with AFK and | * Sort out funding additional possibilities with AFK and Fonds21 and co-write application (in collaboration with Selby, Heerko & Anja) for the Self-driving Canta | ||
Line 21: | Line 21: | ||
• Discuss technical details with location DEK WEST: April 19th/April 20th | • Discuss technical details with location DEK WEST: April 19th/April 20th | ||
• Gather addresses for Open Call: before | • Gather addresses for Open Call: before April 15th | ||
• Prepare Open Call mailing & packages: March 26th - April | • Prepare Open Call mailing & packages: March 26th - April 18th | ||
• Send out Open Call: April | • Send out Open Call: April 16th | ||
• Ultimate deadline application AFK: April 14th | • Ultimate deadline application AFK: April 14th | ||
Revision as of 18:35, 8 April 2018
Summer Academy Production 2018
- Duration: March 1th - August 10th (25 weeks)
- Production / project owner: Anja & Isabel
- Deliverables (subject to change and suggestions)
During the run-up to Summer Academy 2018, Isabel will work on production related activities for this event–in close collaboration with Anja & Juliette (communication). Based on a schedule of 4 hours per week, her main responsibilities (among others) will be:
- Correspondence with the location (DEK WEST) regarding production
- Making inventory of material/equipment/electronics etc necessary
- Gather and order material/equipment
- Arrange caterer for lunch and welcome dinner HDSA 2018
- Possibly arrange a cleaner (maybe arranged via Dek West?)
- Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.)
- Sort out funding additional possibilities with AFK and Fonds21 and co-write application (in collaboration with Selby, Heerko & Anja) for the Self-driving Canta
Planning
• Discuss technical details with location DEK WEST: April 19th/April 20th • Gather addresses for Open Call: before April 15th • Prepare Open Call mailing & packages: March 26th - April 18th • Send out Open Call: April 16th • Ultimate deadline application AFK: April 14th
Budget
The amount of hours spent on this project may vary from week to week (either less or more than 4 hrs). Isabel will monitor her hours to make sure whether or not she exceeds the estimated total.
Total hours: 25 x 4 = 100
Total fee: 100 x €40,00 = €4.000,00 (excl. BTW)