Summer Academy production 2018: Difference between revisions
(Created page with "== Summer Academy Production 2018 == * Duration: March 1th - August 10th (25 weeks) * Production / project owner: Anja & Isabel * Deliverables (subject to change and suggesti...") |
No edit summary |
||
Line 14: | Line 14: | ||
* Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.) | * Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.) | ||
* Sort out funding possibilities with AFK and potentially co-write application (in collaboration with Selby, Heerko & Anja) | * Sort out funding possibilities with AFK and potentially co-write application (in collaboration with Selby, Heerko & Anja) | ||
'''Planning''' | '''Planning''' | ||
Line 22: | Line 23: | ||
• Send out Open Call: April 4th | • Send out Open Call: April 4th | ||
• Ultimate deadline application AFK: April 14th | • Ultimate deadline application AFK: April 14th | ||
'''Budget''' | '''Budget''' | ||
The amount of hours spent on this project may vary from week to week (either less or more than 4 hrs). Isabel will monitor her hours to make sure whether or not she exceeds the estimated total. | The amount of hours spent on this project may vary from week to week (either less or more than 4 hrs). Isabel will monitor her hours to make sure whether or not she exceeds the estimated total. | ||
Total hours: 25 x 4 = 100 | Total hours: 25 x 4 = 100 | ||
Total fee: 100 x €40,00 = €4.000,00 (excl. BTW) | Total fee: 100 x €40,00 = €4.000,00 (excl. BTW) |
Revision as of 09:02, 17 March 2018
Summer Academy Production 2018
- Duration: March 1th - August 10th (25 weeks)
- Production / project owner: Anja & Isabel
- Deliverables (subject to change and suggestions) -- hourly estimate
During the run-up to Summer Academy 2018, Isabel will work on production related activities for this event–in close collaboration with Anja & Juliette (communication). Based on a schedule of 4 hours per week, her main responsibilities (among others) will be:
- Correspondence with the location (DEK WEST) regarding production
- Make inventory of material/equipment/electronics etc necessary
- Gather and order said material/equipment
- Arrange caterer for lunch and welcome dinner HDSA 2018
- possibly arrange a cleaner (maybe arranged via Dek West?)
- Prepare and support HDSA Open Call with Anja and Juliette (gather/sort addresses, send out mailings and packages etc.)
- Sort out funding possibilities with AFK and potentially co-write application (in collaboration with Selby, Heerko & Anja)
Planning
• Discuss technical details with location DEK WEST: April 19th/April 20th • Gather addresses for Open Call: before March 30th • Prepare Open Call mailing & packages: March 26th - April 4th • Send out Open Call: April 4th • Ultimate deadline application AFK: April 14th
Budget
The amount of hours spent on this project may vary from week to week (either less or more than 4 hrs). Isabel will monitor her hours to make sure whether or not she exceeds the estimated total.
Total hours: 25 x 4 = 100
Total fee: 100 x €40,00 = €4.000,00 (excl. BTW)